Pennsylvania State Capitol Building
Harrisburg, Pennsylvania
Peristyle Deck Restoration
Project Background
- Italian Renaissance-style statehouse described by President Teddy Roosevelt as “the handsomest State Capitol I ever saw”
- Capitol’s vaulted dome rises 272 feet and weighs 52 million pounds
- Building contains a large collection of priceless historical artwork
- Leaks through the building’s peristyle decks had been documented as early as the 1950s
- MPS was commissioned to determine where water was entering the building and what should be done to stop the water infiltration; MPS then implemented a pilot phase to set the quality standard for the repairs and prove the efficacy of the preservation approach
Project Challenges
- Asphalt membrane below the decks’ massive granite pavers was keeping water trapped in the system
- Granite pavers needed to be removed and reinstalled in order to access and remove the brick masonry and asphalt membrane; areas had to remain watertight throughout this process
- Significant structural modifications were required to stabilize the large granite deck and facade stone panels and the concrete and masonry sub-structure, including the use of custom stainless steel and Cintec grouted anchors
- Building needed to remain fully operational during restoration process; work area was extremely confined, limiting project progress
Project Approach
- Extensive scaffolding and netting/protection was installed to safely access work areas and protect lower Ludowici tile roofs
- Granite pavers were moved out of the work area, and new reinforced concrete beams and curbs were installed
- A new lead-coated copper roof was installed over the pavers; roof had to mimic the decorative profiles of existing stone walls and column bases
- The new anchorage system was used to structurally bolster the masonry wall assemblies and prevent overturning
- The ornamental granite balustrudes just above the pavers were also disassembled and restored as part of the peristyle deck restoration
“MPS delivers value during every stage of a project, be it during project conception or during construction. At the Pennsylvania State Capitol they developed a carefully thought-out waterproofing design solution. During a subsequent pilot program, they successfully implemented the work as conceived by the design team. Their decades of experience, creativity, and problem-solving make them a truly invaluable part of the team.”
Niklas W. Vigener
Senior Principal
Simpson Gumpertz & Heger